Silver Bridge Closure and Recovery
The Silver Bridge in the Town of Bracebridge is fully closed to all vehicle and pedestrian traffic in both directions while a detailed structural assessment is underway.
May 8, 2026 Update:
Work projected between May 11 and May 15, 2026:
- Installation and pouring of concrete to support temporary structural work at the north end of the bridge
- Ongoing strengthening of the bridge’s steel truss structure
- Continued work on retaining walls near Ecclestone Drive, including installing reinforcing connections
April 27, 2026 Update:
Work completed between April 20 and April 24, 2026:
- Continued partial depth concrete removals from retaining walls
- Installed scaffolding / access for truss strengthening
- Started truss strengthening
Work projected between April 27 and May 1, 2026:
- Install additional access and scaffolding for truss strengthening
- Continue truss member reinforcing
- Complete partial depth concrete removal on wall
April 17, 2026 Update:
Monday, April 20 - Crews will be adding reinforcement to the bridge's structural supports and setting up access for workers. At the Ecclestone Drive retaining walls, workers will be removing sections of concrete and setting up site access.
Tuesday, April 21 - Crews will continue adding reinforcement to the bridge's structural supports. At the Ecclestone Drive retaining walls, work continues on concrete removal, including measuring and inspecting the areas where concrete has been removed to determine if deeper removal is needed.
Wednesday, April 22 to Friday, April 24 - Crews will continue adding reinforcement to the bridge's structural supports. At the Ecclestone Drive retaining walls, workers will be doing more extensive concrete removal.
April 10, 2026 Update:
Construction work on Silver Bridge for the week of April 13 to 17 activities include:
Monday, April 13: Scaffolding and access equipment will be installed to support upcoming structural strengthening work. Crews will begin removing sections of concrete from the retaining walls and setting up site access.
Tuesday, April 14: Bracing and blocking will be installed, and structural strengthening of the bridge trusses will begin. Concrete removal and access work will continue with the retaining walls.
Wednesday, April 15 to Friday, April 17: Structural strengthening of the bridge trusses will continue. Concrete removal and access work will continue with the retaining walls.
Feb. 3, 2026 Update:
A detailed structural review and rehabilitation plan was completed and repair work is now underway.
Clearwater Structures Inc. are on site this week installing a temporary support structure that will be used during construction. The bridge is scheduled to reopen by the end of 2026.
Detour Information
Detours: Detour routes are in place for safe travel to and from the Main Street area. Most drivers will only experience minimal delays.
Navigation Apps: Municipal 511 has been updated with detour information, helping to keep Google Maps and Waze current.
Updates: We’ll continue to share updates as they become available.
We appreciate your patience and cooperation as we work to ensure the safety of everyone using District infrastructure. Updates will be shared as they become available.
Background
In early January 2025, Bracebridge Operations staff noticed that the clearance for sidewalk equipment on the bridge looked different than usual. This prompted a closer inspection by District staff and a Senior Structural Engineer, which revealed some deformation in the bridge’s truss members.
A careful, expert-driven selection process
Before selecting Clearwater Construction, the District undertook a detailed and deliberate process to ensure the bridge could be safely rehabilitated and that the most qualified contractor was chosen.
This work included:
- Conducting an in-depth analysis of the failed structural condition and assessing the feasibility of rehabilitation.
- Evaluating how weight and loading were distributed across the bridge under the damaged condition.
- Consulting with industry experts to determine the safest and most effective rehabilitation approach.
- Requesting and reviewing expressions of interest from experienced heavy civil contractors and shortlisting the top three firms based on expertise and capacity.
- Interviewing shortlisted contractors, clarifying scope, and reviewing detailed technical and cost proposals before selecting a preferred partner.
This new, two-stage selection process was designed to secure the best industry expertise at the best overall value, ensuring the rehabilitation is completed safely, efficiently, and to the highest engineering standards.






