Weekly Project Update - July 27
Work planned week of July 27 to July 31
- The crew will continue installation of the spine beam launching mechanism (a temporary structural “backbone” for the engineered jacking system), launch spine beams, install sidewalk strong backs and plan to pour another section of the concrete retaining wall refacing.
- Crews will be on site Saturday, July 25.
Work completed week of July 20 to July 24
- Contractor continued the alignment and installation of the spine beam launching mechanism at the north approach, such as temporary cribbing, channels and roller beams/rails.
- A separate crew worked to install scaffolding, dowels, mesh and forms on the Ecclestone drive retaining wall.
Community impacts
- No new impacts to residents or pedestrians currently.
Share Weekly Project Update - July 27 on Facebook
Share Weekly Project Update - July 27 on X (formerly Twitter)
Share Weekly Project Update - July 27 on Linkedin
Email Weekly Project Update - July 27 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends