Work planned Week of July 20 to 24
- Crews will be working on site on Saturday, July 18. Construction activities will be limited to the work zone on the bridge.
- Crews will keep setting up and lining up the equipment used to place the main bridge beam.
- Crews plan to pour another section of the concrete retaining wall.
Work completed Week of July 13 to 17
- Crews finished the supports at the top of the bridge piers.
- Crews began setting up the equipment used to place the main bridge beam at the north end of the bridge. This included temporary supports and rails to help guide the beam into place.
- A separate crew set up scaffolding, metal rods, mesh, and forms on the retaining wall along Ecclestone Drive, getting it ready for another concrete pour.
Community impacts
No major impacts are expected right now.
Share Weekly Project Update - July 20 on Facebook
Share Weekly Project Update - July 20 on X (formerly Twitter)
Share Weekly Project Update - July 20 on Linkedin
Email Weekly Project Update - July 20 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends