Weekly Project Update - August 10

Work planned week of August 10 to August 14

  • Installation of equipment on the south side of the bridge that will be used to move the large spine beams into place.
  • Installation of the bridge jacking equipment on the north side of the bridge, including rollers, jacks, and other supporting components, in preparation for lifting the bridge.
  • Installation of steel dowels, wire mesh, and formwork for the Ecclestone Drive retaining wall.

Work completed week of August 3 to August 7

  • Continued installation of the spine beam launching mechanism at the south end of the bridge (used to lift and move the large spine beams into place) and moved the spine beams into position in preparation for bridge jacking.
  • Temporary supports installed to reinforce sidewalk sections during bridge jacking.
  • Refaced another section of the south concrete retaining wall.

Community impacts
No new impacts to residents or pedestrians currently.