Weekly Project Update - August 3

Work planned week of August 3 to August 7

  • View of the temporary rail system for the spine beam launch. Continue installation of the spine beam launching mechanism at the south end of the bridge (used to lift and move the large spine beams into place) and move the spine beams into position in preparation for bridge jacking.
  • Temporary supports will be installed to reinforce sidewalk sections during bridge jacking.
  • Reface another section of the south concrete retaining wall.

Work completed week of July 27 to July 31

  • Crews completed the alignment and installation of the spine beam launching mechanism at the north end of the bridge, including temporary supports for lifting the beams into place.
  • Installation of concrete forms (to hold concrete in place while it's poured) along the Ecclestone drive retaining wall.

Community impacts
No new impacts to residents or pedestrians currently.