Weekly Project Update - September 4
Work planned week of September 7 to September 11
- Continue permanent structural steel repairs to the main truss now that the bridge is in the temporarily supported condition.
- Install wood formwork to complete another section of concrete refacing along the Ecclestone Drive retaining wall.
Work completed week of August 31 to September 4
- Removal of old structural steel components to be replaced.
- Sandblasting (high pressure air that blasts abrasive particles to clean a surface) and priming of existing steel to remain prior to installing new steel replacement components.
- Completed a concrete pour on the Ecclestone Drive retaining wall refacing.
Community impacts
- There are no new impacts for residents or pedestrians this week.
Share Weekly Project Update - September 4 on Facebook
Share Weekly Project Update - September 4 on X (formerly Twitter)
Share Weekly Project Update - September 4 on Linkedin
Email Weekly Project Update - September 4 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends