Weekly Project Update - September 4

Work planned week of September 7 to September 11

  • Continue permanent structural steel repairs to the main truss now that the bridge is in the temporarily supported condition.
  • Install wood formwork to complete another section of concrete refacing along the Ecclestone Drive retaining wall.

Work completed week of August 31 to September 4

  • Removal of old structural steel components to be replaced.
  • Sandblasting (high pressure air that blasts abrasive particles to clean a surface) and priming of existing steel to remain prior to installing new steel replacement components.
  • Completed a concrete pour on the Ecclestone Drive retaining wall refacing.

Community impacts

  • There are no new impacts for residents or pedestrians this week.