Weekly Project Update - Jul 6 to 10

Work planned week of July 6 to July 10

  • Continue to work on installation of temporary steel reinforcement including upper vertical supports at piers and jacking connections
  • Continue to install mesh, dowels and framework at Ecclestone Drive retaining wall

Work completed week of June 29 to July 3

  • Crews continued installing temporary steel supports, including vertical supports at the bridge piers and jacking supports.
  • Continuing with retaining wall resurfacing along Ecclestone Drive

Community impacts

  • There are currently no new community impacts to note.