Weekly Project Update - July 13 to 19

Work planned Week of July 13 to July 17

  • Complete the installation of temporary steel reinforcement including upper vertical supports at piers, bracing and jacking connections.
  • Start the installation and alignment of the spine beam launching mechanism (a temporary structural “backbone” for the engineered jacking system) and continue to install mesh, dowels and formwork at the Ecclestone Drive retaining wall.

Work completed Week of July 6 to July 10

  • Contractor continued installation of all temporary steel reinforcement including upper vertical supports at piers.
  • Formwork from the concrete retaining wall refacing along Ecclestone Drive was removed and small holes left from the wall forms were patched/filled in.

Community impacts
Nothing new to note.