Muskoka Rd. 117, Baysville - A 'Muskoka Main Streets' Initiative

Share Muskoka Rd. 117, Baysville - A 'Muskoka Main Streets' Initiative on Facebook Share Muskoka Rd. 117, Baysville - A 'Muskoka Main Streets' Initiative on X (formerly Twitter) Share Muskoka Rd. 117, Baysville - A 'Muskoka Main Streets' Initiative on Linkedin Email Muskoka Rd. 117, Baysville - A 'Muskoka Main Streets' Initiative link

The District of Muskoka and the Township of Lake of Bays are working together on the first ever 'Muskoka Main Streets' project, starting in Baysville. This initiative was created to strengthen the places where residents live, work, and connect, because main streets are more than just roads. They’re community gateways, economic corridors, and shared spaces.

By enhancing existing roads and building new infrastructure, we’re strengthening the foundation of our communities, supporting local economic growth, improving safety for all road and sidewalk users, and creating inviting spaces for residents, workers, and visitors alike.

This project will redevelop a 780-metre section of Muskoka Rd. 117 through the Community of Baysville. In addition to upgrading the existing road surface, the project will improve traffic flow and enhance safety for both pedestrians and drivers through traffic calming features, with a modern roundabout and pedestrian crossings. It will also add active transportation infrastructure, including a new multi-use trail and a sidewalk.

The Lake of Bays - Community Improvement Plan (External Link) was shaped by two surveys with nearly 500 responses, as well as multiple public information sessions. A key theme from the community's feedback was the need to improve the section of Muskoka Rd. 117 in Baysville.

Baysville was chosen as the first project for this program, making it a model for future initiatives across Muskoka that improve walkability, support local business, and enhance public space.

Please note that all dates and durations are subject to change due to weather, supply availability, or other unforeseen circumstances.


Project Purpose & Goals

This project responds directly to community feedback gathered through two public surveys and multiple engagement sessions. This investment also reflects a broader goal to develop consistent, high-quality, main street experiences across Muskoka's communities.

Residents called for:
* Safer pedestrian and cycling routes,
* Slower traffic through town,
* A more attractive and welcoming streetscape, and
* Better connectivity for local businesses, residents, and visitors.

What to Expect During Construction


What to Expect After Construction

🚧 New Traffic Patterns
Expect temporary adjustments as construction moves forward, with clear timelines and minimal disruption.

⚠️ Clear, Simple Signage
Watch for easy-to-navigate signs to help guide both drivers and pedestrians safely through the area.

🛑 Safety Barriers
Short-term barriers will help protect pedestrians and workers while work is underway.

🌦️ Built for Muskoka's Weather
Our upgrades are designed with all four seasons in mind. Construction will pause during the colder months and resume in Spring 2026.

🔁 Designed to Evolve
This project is built to grow with Baysville, improving how we live, move, and connect.


🚗 Traffic Calming Features
New design elements will encourage safer, slower driving to support a more pedestrian-friendly environment.

🚶‍♀️ Raised Pedestrian Crossings
These visible crossings will help prioritize pedestrian safety and improve walkability throughout the area.

Modern Roundabout
A new roundabout will support better traffic flow while making intersections safer for drivers, cyclists, and pedestrians.

/┆\ Enhanced Streetscape
Expect thoughtful landscaping, durable materials, and weather-ready features built to look great year-round.




Why Build a Roundabout on a Highway Through Town?
Improved SafetyA roundabout reduces the risk of serious crashes by slowing down vehicles and eliminating dangerous left turns and head on collisions.
Better Traffic FlowA roundabout keeps vehicles moving. This helps reduce congestion and delays, especially during busy times or tourist seasons.
Support for Local DevelopmentThis feature can help manage increased traffic from new housing, businesses, or recreational areas, making it easier for drivers to enter and exit side streets safely.
Gateway FeatureA roundabout can act as a visual “gateway” into the community, signalling to drivers that they’re entering a populated area. It encourages slower speeds and can be landscaped to reflect local identity.
Environmental BenefitsBecause vehicles don’t idle as long, they can reduce fuel use and emissions, supporting sustainability goals.



Why Now?

This project is part of a long term commitment to build safer, more vibrant communities across Muskoka. With regular updates, clear signage, and transparent communication, we'll keep you informed every step of the way.


If you have any comments or questions please fill out our Comments or Questions Form below.

The District of Muskoka and the Township of Lake of Bays are working together on the first ever 'Muskoka Main Streets' project, starting in Baysville. This initiative was created to strengthen the places where residents live, work, and connect, because main streets are more than just roads. They’re community gateways, economic corridors, and shared spaces.

By enhancing existing roads and building new infrastructure, we’re strengthening the foundation of our communities, supporting local economic growth, improving safety for all road and sidewalk users, and creating inviting spaces for residents, workers, and visitors alike.

This project will redevelop a 780-metre section of Muskoka Rd. 117 through the Community of Baysville. In addition to upgrading the existing road surface, the project will improve traffic flow and enhance safety for both pedestrians and drivers through traffic calming features, with a modern roundabout and pedestrian crossings. It will also add active transportation infrastructure, including a new multi-use trail and a sidewalk.

The Lake of Bays - Community Improvement Plan (External Link) was shaped by two surveys with nearly 500 responses, as well as multiple public information sessions. A key theme from the community's feedback was the need to improve the section of Muskoka Rd. 117 in Baysville.

Baysville was chosen as the first project for this program, making it a model for future initiatives across Muskoka that improve walkability, support local business, and enhance public space.

Please note that all dates and durations are subject to change due to weather, supply availability, or other unforeseen circumstances.


Project Purpose & Goals

This project responds directly to community feedback gathered through two public surveys and multiple engagement sessions. This investment also reflects a broader goal to develop consistent, high-quality, main street experiences across Muskoka's communities.

Residents called for:
* Safer pedestrian and cycling routes,
* Slower traffic through town,
* A more attractive and welcoming streetscape, and
* Better connectivity for local businesses, residents, and visitors.

What to Expect During Construction


What to Expect After Construction

🚧 New Traffic Patterns
Expect temporary adjustments as construction moves forward, with clear timelines and minimal disruption.

⚠️ Clear, Simple Signage
Watch for easy-to-navigate signs to help guide both drivers and pedestrians safely through the area.

🛑 Safety Barriers
Short-term barriers will help protect pedestrians and workers while work is underway.

🌦️ Built for Muskoka's Weather
Our upgrades are designed with all four seasons in mind. Construction will pause during the colder months and resume in Spring 2026.

🔁 Designed to Evolve
This project is built to grow with Baysville, improving how we live, move, and connect.


🚗 Traffic Calming Features
New design elements will encourage safer, slower driving to support a more pedestrian-friendly environment.

🚶‍♀️ Raised Pedestrian Crossings
These visible crossings will help prioritize pedestrian safety and improve walkability throughout the area.

Modern Roundabout
A new roundabout will support better traffic flow while making intersections safer for drivers, cyclists, and pedestrians.

/┆\ Enhanced Streetscape
Expect thoughtful landscaping, durable materials, and weather-ready features built to look great year-round.




Why Build a Roundabout on a Highway Through Town?
Improved SafetyA roundabout reduces the risk of serious crashes by slowing down vehicles and eliminating dangerous left turns and head on collisions.
Better Traffic FlowA roundabout keeps vehicles moving. This helps reduce congestion and delays, especially during busy times or tourist seasons.
Support for Local DevelopmentThis feature can help manage increased traffic from new housing, businesses, or recreational areas, making it easier for drivers to enter and exit side streets safely.
Gateway FeatureA roundabout can act as a visual “gateway” into the community, signalling to drivers that they’re entering a populated area. It encourages slower speeds and can be landscaped to reflect local identity.
Environmental BenefitsBecause vehicles don’t idle as long, they can reduce fuel use and emissions, supporting sustainability goals.



Why Now?

This project is part of a long term commitment to build safer, more vibrant communities across Muskoka. With regular updates, clear signage, and transparent communication, we'll keep you informed every step of the way.


If you have any comments or questions please fill out our Comments or Questions Form below.

  • Weekly Project Update - August 17

    Share Weekly Project Update - August 17 on Facebook Share Weekly Project Update - August 17 on X (formerly Twitter) Share Weekly Project Update - August 17 on Linkedin Email Weekly Project Update - August 17 link

    Work planned week of August 17 to 21

    • Crews will prepare the boulevards between Dickie and Bay Street for paving and continue work on Lena Street access.
    • Depending on weather, lay asphalt on the boulevards, pour remaining concrete curbs, and install rest areas.

    Work completed week of August 10 to 14

    • The sidewalk and curb between Dickie Street and Bay Street are complete, including tactile plates (raised surfaces that help people who are visually impaired navigate the crossing).
    • Lena Street was cleared of vegetation and roots, and a new layer of compacted gravel base was added.

    Community impacts

    • No new community impacts are anticipated this week.

    Work planned week of August 17 to 21

    • Crews will prepare the boulevards between Dickie and Bay Street for paving and continue work on Lena Street access.
    • Depending on weather, lay asphalt on the boulevards, pour remaining concrete curbs, and install rest areas.

    Work completed week of August 10 to 14

    • The sidewalk and curb between Dickie Street and Bay Street are complete, including tactile plates (raised surfaces that help people who are visually impaired navigate the crossing).
    • Lena Street was cleared of vegetation and roots, and a new layer of compacted gravel base was added.

    Community impacts

    • No new community impacts are anticipated this week.
  • Weekly Project Update - August 10

    Share Weekly Project Update - August 10 on Facebook Share Weekly Project Update - August 10 on X (formerly Twitter) Share Weekly Project Update - August 10 on Linkedin Email Weekly Project Update - August 10 link

    Work planned week of August 10 to August 14

    • Continue sidewalk construction on the north side of Muskoka Road 117 toward Bay Street.
    • Place the second lift of asphalt, weather permitting.
    • Begin forming and pouring concrete bases for pedestrian crossing infrastructure.

    Work completed week of August 3 to August 7

    • Completed sidewalk construction on the south side of Muskoka Road 117 from University Street to the bridge.
    • Installed crosswalk wiring.

    Community impacts
    Occasional single-lane closures may occur, depending on paving activities

    Work planned week of August 10 to August 14

    • Continue sidewalk construction on the north side of Muskoka Road 117 toward Bay Street.
    • Place the second lift of asphalt, weather permitting.
    • Begin forming and pouring concrete bases for pedestrian crossing infrastructure.

    Work completed week of August 3 to August 7

    • Completed sidewalk construction on the south side of Muskoka Road 117 from University Street to the bridge.
    • Installed crosswalk wiring.

    Community impacts
    Occasional single-lane closures may occur, depending on paving activities

  • Weekly Project Update - August 3

    Share Weekly Project Update - August 3 on Facebook Share Weekly Project Update - August 3 on X (formerly Twitter) Share Weekly Project Update - August 3 on Linkedin Email Weekly Project Update - August 3 link

    Work planned week of August 3 to August 7

    • Crews will continue sidewalk work and begin installing the new pedestrian crossing, including the electrical work needed to power the crossing.
    • Landscaping will begin to tidy up and finish the surrounding area.

    Work completed week of July 27 to July 31

    • Crews prepared the ground where the new pedestrian crossing will go.
    • Water and sewer connections complete.

    Community impacts

    • No new impacts to residents or pedestrians this week.

    Work planned week of August 3 to August 7

    • Crews will continue sidewalk work and begin installing the new pedestrian crossing, including the electrical work needed to power the crossing.
    • Landscaping will begin to tidy up and finish the surrounding area.

    Work completed week of July 27 to July 31

    • Crews prepared the ground where the new pedestrian crossing will go.
    • Water and sewer connections complete.

    Community impacts

    • No new impacts to residents or pedestrians this week.
  • Weekly Project Update - July 27

    Share Weekly Project Update - July 27 on Facebook Share Weekly Project Update - July 27 on X (formerly Twitter) Share Weekly Project Update - July 27 on Linkedin Email Weekly Project Update - July 27 link

    Work Planned: Week of July 27 to 31Crews have begun work on the multi-use trail.

    • Continuing sidewalk construction
    • Landscaping and restoration work in areas where construction is complete

    Work Completed: Week of July 20 to 24

    • Installed concrete curbs
    • Graded the ground to prepare for new sidewalks

    • Installed water and sewer service connections
    • Completed electrical work to prepare for the new pedestrian crossovers (PXOs) and streetlights

    Community impacts

    • No new impacts to residents or pedestrians currently.

    Work Planned: Week of July 27 to 31Crews have begun work on the multi-use trail.

    • Continuing sidewalk construction
    • Landscaping and restoration work in areas where construction is complete

    Work Completed: Week of July 20 to 24

    • Installed concrete curbs
    • Graded the ground to prepare for new sidewalks

    • Installed water and sewer service connections
    • Completed electrical work to prepare for the new pedestrian crossovers (PXOs) and streetlights

    Community impacts

    • No new impacts to residents or pedestrians currently.
  • Weekly Project Update - July 20

    Share Weekly Project Update - July 20 on Facebook Share Weekly Project Update - July 20 on X (formerly Twitter) Share Weekly Project Update - July 20 on Linkedin Email Weekly Project Update - July 20 link

    Work Planned July 20 to 26

    • Sidewalk installation continues
    • Crews will grade the roadbed to prepare for paving, which levels and compacts the surface to allow asphalt to be laid evenly

    Work Completed July 13 to 19

    • Curb installation is now finished
    • A driveway was relocated to align with the new road design

    Community Impacts

    • Traffic will continue to be reduced to one lane in the work zone, with flaggers directing drivers through.

    Work Planned July 20 to 26

    • Sidewalk installation continues
    • Crews will grade the roadbed to prepare for paving, which levels and compacts the surface to allow asphalt to be laid evenly

    Work Completed July 13 to 19

    • Curb installation is now finished
    • A driveway was relocated to align with the new road design

    Community Impacts

    • Traffic will continue to be reduced to one lane in the work zone, with flaggers directing drivers through.
  • Weekly Project Update - July 13

    Share Weekly Project Update - July 13 on Facebook Share Weekly Project Update - July 13 on X (formerly Twitter) Share Weekly Project Update - July 13 on Linkedin Email Weekly Project Update - July 13 link

    Work planned Week of July 13 to July 20

    • Finish all concrete curb work
    • Installation of sewers and water lines
    • Second layer of asphalt will begin when water and sewer work is completed.

    Work completed Week of July 6 to July 10

    • First layer of Asphalt completed.

    Community Impacts
    There are no new community impacts at this time.

    Work planned Week of July 13 to July 20

    • Finish all concrete curb work
    • Installation of sewers and water lines
    • Second layer of asphalt will begin when water and sewer work is completed.

    Work completed Week of July 6 to July 10

    • First layer of Asphalt completed.

    Community Impacts
    There are no new community impacts at this time.

  • Weekly Project Update - July 6

    Share Weekly Project Update - July 6 on Facebook Share Weekly Project Update - July 6 on X (formerly Twitter) Share Weekly Project Update - July 6 on Linkedin Email Weekly Project Update - July 6 link

    Work planned week of July 6 to July 10

    • Curb on south side of roundabout
    • Completion of storm sewer from Dickie Street to Bay Street
    • Paving multi-use trail

    Work completed week of June 29 to July 3

    • Paving base course Brunel Road to Bay Street.
    • Storm Sewer between Dickie Street and Bay Street.

    Community impacts

    • Two lane traffic flow on paved roadway with some lane reductions controlled by traffic control personnel during working hours.

    Work planned week of July 6 to July 10

    • Curb on south side of roundabout
    • Completion of storm sewer from Dickie Street to Bay Street
    • Paving multi-use trail

    Work completed week of June 29 to July 3

    • Paving base course Brunel Road to Bay Street.
    • Storm Sewer between Dickie Street and Bay Street.

    Community impacts

    • Two lane traffic flow on paved roadway with some lane reductions controlled by traffic control personnel during working hours.
  • Weekly Project Update - June 29

    Share Weekly Project Update - June 29 on Facebook Share Weekly Project Update - June 29 on X (formerly Twitter) Share Weekly Project Update - June 29 on Linkedin Email Weekly Project Update - June 29 link

    Work planned for week of June 27 to July 3

    • Curb installation on south side of the roundabout.

    • Road base material will be placed and graded to the proper elevation in preparation for paving.

    • A first lift of asphalt will be paved along a section of the roundabout to Bay Street.

    • Storm water installation will be completed from Dickie Street to Bay Street.

    Work completed week of June 22 to June 26

    • Road base material was placed along the construction corridor.

    • Storm Sewer installation progressed between Dickie Street and Bay Street.

    • Rough Grading of sidewalk areas was completed.


    Community impacts

    • Regular single lane traffic flow during work hours with on-site traffic flagging personnel will continue.

    Work planned for week of June 27 to July 3

    • Curb installation on south side of the roundabout.

    • Road base material will be placed and graded to the proper elevation in preparation for paving.

    • A first lift of asphalt will be paved along a section of the roundabout to Bay Street.

    • Storm water installation will be completed from Dickie Street to Bay Street.

    Work completed week of June 22 to June 26

    • Road base material was placed along the construction corridor.

    • Storm Sewer installation progressed between Dickie Street and Bay Street.

    • Rough Grading of sidewalk areas was completed.


    Community impacts

    • Regular single lane traffic flow during work hours with on-site traffic flagging personnel will continue.

  • Roundabout is now open for motorists

    Share Roundabout is now open for motorists on Facebook Share Roundabout is now open for motorists on X (formerly Twitter) Share Roundabout is now open for motorists on Linkedin Email Roundabout is now open for motorists link
    supporting image

    Great news! The roundabout portion of the MR117 project is now open for motorists.

    Great news! The roundabout portion of the MR117 project is now open for motorists.

  • Join us at the next Construction Café: Friday, June 26

    Share Join us at the next Construction Café: Friday, June 26 on Facebook Share Join us at the next Construction Café: Friday, June 26 on X (formerly Twitter) Share Join us at the next Construction Café: Friday, June 26 on Linkedin Email Join us at the next Construction Café: Friday, June 26 link
    supporting image

    Curious about how the MR 117 Muskoka Main Streets project is moving along? Have questions?
    Join us at the upcoming Construction Café! This is a relaxed, come-and-go gathering.
    Grab a coffee, connect with the team, and ask your questions.

    📍Baysville Library, 10 University St.
    🗓️ June 26 | 11 a.m. to 2 p.m.

    Come by anytime between these hours. We’d love to see you there!



    Curious about how the MR 117 Muskoka Main Streets project is moving along? Have questions?
    Join us at the upcoming Construction Café! This is a relaxed, come-and-go gathering.
    Grab a coffee, connect with the team, and ask your questions.

    📍Baysville Library, 10 University St.
    🗓️ June 26 | 11 a.m. to 2 p.m.

    Come by anytime between these hours. We’d love to see you there!



Page last updated: 17 Aug 2026, 11:35 AM