Project Update - June 29 to July 3

Work planned for week of June 27 to July 3

  • Curb installation on south side of the roundabout.

  • Road base material will be placed and graded to the proper elevation in preparation for paving.

  • A first lift of asphalt will be paved along a section of the roundabout to Bay Street.

  • Storm water installation will be completed from Dickie Street to Bay Street.

Work completed week of June 22 to June 26

  • Road base material was placed along the construction corridor.

  • Storm Sewer installation progressed between Dickie Street and Bay Street.

  • Rough Grading of sidewalk areas was completed.


Community impacts

  • Regular single lane traffic flow during work hours with on-site traffic flagging personnel will continue.

Share Project Update - June 29 to July 3 on Facebook Share Project Update - June 29 to July 3 on X (formerly Twitter) Share Project Update - June 29 to July 3 on Linkedin Email Project Update - June 29 to July 3 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>