Project Update - June 29 to July 3
Work planned for week of June 27 to July 3
Curb installation on south side of the roundabout.
Road base material will be placed and graded to the proper elevation in preparation for paving.
A first lift of asphalt will be paved along a section of the roundabout to Bay Street.
Storm water installation will be completed from Dickie Street to Bay Street.
Work completed week of June 22 to June 26
Road base material was placed along the construction corridor.
Storm Sewer installation progressed between Dickie Street and Bay Street.
Rough Grading of sidewalk areas was completed.
Community impacts
Regular single lane traffic flow during work hours with on-site traffic flagging personnel will continue.