Weekly Project Update - August 3

Work planned week of August 3 to August 7

  • Crews will continue sidewalk work and begin installing the new pedestrian crossing, including the electrical work needed to power the crossing.
  • Landscaping will begin to tidy up and finish the surrounding area.

Work completed week of July 27 to July 31

  • Crews prepared the ground where the new pedestrian crossing will go.
  • Water and sewer connections complete.

Community impacts

  • No new impacts to residents or pedestrians this week.