Weekly Project Update - July 20
Work Planned July 20 to 26
- Sidewalk installation continues
- Crews will grade the roadbed to prepare for paving, which levels and compacts the surface to allow asphalt to be laid evenly
Work Completed July 13 to 19
- Curb installation is now finished
- A driveway was relocated to align with the new road design
Community Impacts
- Traffic will continue to be reduced to one lane in the work zone, with flaggers directing drivers through.
Share Weekly Project Update - July 20 on Facebook
Share Weekly Project Update - July 20 on X (formerly Twitter)
Share Weekly Project Update - July 20 on Linkedin
Email Weekly Project Update - July 20 link