Weekly Project Update - July 6

Work planned week of July 6 to July 10

  • Curb on south side of roundabout
  • Completion of storm sewer from Dickie Street to Bay Street
  • Paving multi-use trail

Work completed week of June 29 to July 3

  • Paving base course Brunel Road to Bay Street.
  • Storm Sewer between Dickie Street and Bay Street.

Community impacts

  • Two lane traffic flow on paved roadway with some lane reductions controlled by traffic control personnel during working hours.