Weekly Project Update - August 10

Work planned week of August 10 to August 14

  • Continue sidewalk construction on the north side of Muskoka Road 117 toward Bay Street.
  • Place the second lift of asphalt, weather permitting.
  • Begin forming and pouring concrete bases for pedestrian crossing infrastructure.

Work completed week of August 3 to August 7

  • Completed sidewalk construction on the south side of Muskoka Road 117 from University Street to the bridge.
  • Installed crosswalk wiring.

Community impacts
Occasional single-lane closures may occur, depending on paving activities