Weekly Project Update - July 13
Work planned Week of July 13 to July 20
- Finish all concrete curb work
- Installation of sewers and water lines
- Second layer of asphalt will begin when water and sewer work is completed.
Work completed Week of July 6 to July 10
- First layer of Asphalt completed.
Community Impacts
There are no new community impacts at this time.