Muskoka Road 118 West - Safety Updates

Share Muskoka Road 118 West - Safety Updates on Facebook Share Muskoka Road 118 West - Safety Updates on X (formerly Twitter) Share Muskoka Road 118 West - Safety Updates on Linkedin Email Muskoka Road 118 West - Safety Updates link


August 11, 2026
Community Update – Muskoka Road 118 at Westmall Road (‘the Flats’)

Temporary concrete barriers were installed in early 2025 on Muskoka Road (MR) 118W between Balls Drive and Westmall Road to make the area safer for drivers, pedestrians, and businesses along the corridor by removing hazards created by left turning vehicles.

Based on feedback from the community, and now that driver behaviour has adapted to the changes, the current set up is being replaced with a concrete curb and asphalt median while the District reviews options for the road’s future design and completes the environmental review required by the Province. The review will define both the road and underground servicing (water and sewer infrastructure) through the area. The future design will continue to restrict left-turns through this area but will include enhanced infrastructure to provide easier movement of traffic.

Why are left turns restricted?

Between January 2020 and October 2024, there were 29 collisions on this stretch of Muskoka Road 118, including a fatality.

The study found that left turns and crossing movements at entrances along this corridor were dangerous with drivers needing to cross several lanes of busy traffic to get in or out.

Specific concerns included:

  • Drivers crossing up to five lanes of traffic as part of their turning or crossing movement
  • Cars waiting to turn left blocking the lane behind them while waiting for a gap
  • Hills and property elevation made it hard for drivers to see oncoming traffic
  • Numerous close calls between cars, pedestrians, and trucks, especially in the busier summer months

These left-turn and through restrictions are a direct response to the accident history, field observations and a full engineering review on this section of MR 118.

The District's goal is to prevent serious collisions and maintain safe access for local businesses, motorists, and pedestrians.

Improvements made to enhance safety

  • Eliminated left turns (and crossing the road) at entrances using barriers and signage
  • Repainted and improved road markings
  • Sending drivers to nearby traffic lights to turn safely, instead of crossing multiple lanes from a private driveway

The study looked at several options and found that removing left turns and crossing movements improves safety without causing major traffic backups.

What's next?

The District is currently working on a preliminary concept design and environmental review for the corridor, which will consider:

  • Rebuilding this stretch of MR 118W with a permanent median restricting left turns
  • Water, storm, and sanitary sewer improvements and potential capacity expansion
  • Intersection and active transportation improvements along the corridor

Together, these changes aim to make the road safer and keep traffic moving.



Support for businesses in 'the flats'

We posted resources, updates, and information to help businesses stay informed of the changes.


August 11, 2026
Community Update – Muskoka Road 118 at Westmall Road (‘the Flats’)

Temporary concrete barriers were installed in early 2025 on Muskoka Road (MR) 118W between Balls Drive and Westmall Road to make the area safer for drivers, pedestrians, and businesses along the corridor by removing hazards created by left turning vehicles.

Based on feedback from the community, and now that driver behaviour has adapted to the changes, the current set up is being replaced with a concrete curb and asphalt median while the District reviews options for the road’s future design and completes the environmental review required by the Province. The review will define both the road and underground servicing (water and sewer infrastructure) through the area. The future design will continue to restrict left-turns through this area but will include enhanced infrastructure to provide easier movement of traffic.

Why are left turns restricted?

Between January 2020 and October 2024, there were 29 collisions on this stretch of Muskoka Road 118, including a fatality.

The study found that left turns and crossing movements at entrances along this corridor were dangerous with drivers needing to cross several lanes of busy traffic to get in or out.

Specific concerns included:

  • Drivers crossing up to five lanes of traffic as part of their turning or crossing movement
  • Cars waiting to turn left blocking the lane behind them while waiting for a gap
  • Hills and property elevation made it hard for drivers to see oncoming traffic
  • Numerous close calls between cars, pedestrians, and trucks, especially in the busier summer months

These left-turn and through restrictions are a direct response to the accident history, field observations and a full engineering review on this section of MR 118.

The District's goal is to prevent serious collisions and maintain safe access for local businesses, motorists, and pedestrians.

Improvements made to enhance safety

  • Eliminated left turns (and crossing the road) at entrances using barriers and signage
  • Repainted and improved road markings
  • Sending drivers to nearby traffic lights to turn safely, instead of crossing multiple lanes from a private driveway

The study looked at several options and found that removing left turns and crossing movements improves safety without causing major traffic backups.

What's next?

The District is currently working on a preliminary concept design and environmental review for the corridor, which will consider:

  • Rebuilding this stretch of MR 118W with a permanent median restricting left turns
  • Water, storm, and sanitary sewer improvements and potential capacity expansion
  • Intersection and active transportation improvements along the corridor

Together, these changes aim to make the road safer and keep traffic moving.



Support for businesses in 'the flats'

We posted resources, updates, and information to help businesses stay informed of the changes.

  • Project Update - October 2

    Share Project Update - October 2 on Facebook Share Project Update - October 2 on X (formerly Twitter) Share Project Update - October 2 on Linkedin Email Project Update - October 2 link

    Temporary Barrier Installation Complete

    Work completed week of September 28 to October 2

    • Crews placed new asphalt between the curbs and to tie into existing asphalt.
    • Old traffic paint in the middle of the road was removed and new traffic paint lines were installed.
    • Temporary traffic control measures were removed and both lanes of traffic were opened in each direction.

    Community impact

    • Both lanes of traffic in each direction are now reopened.

    Temporary Barrier Installation Complete

    Work completed week of September 28 to October 2

    • Crews placed new asphalt between the curbs and to tie into existing asphalt.
    • Old traffic paint in the middle of the road was removed and new traffic paint lines were installed.
    • Temporary traffic control measures were removed and both lanes of traffic were opened in each direction.

    Community impact

    • Both lanes of traffic in each direction are now reopened.
  • Project Update - September 28

    Share Project Update - September 28 on Facebook Share Project Update - September 28 on X (formerly Twitter) Share Project Update - September 28 on Linkedin Email Project Update - September 28 link

    Work planned week of September 28 to October 2

    • Asphalt paving   

    • Line painting

    Work completed the week of September 21 to September 25 

    • The concrete curb was completed  

    • Gravel filled around curb (below asphalt) 

    Community impact

    • Single lane closures will remain throughout the month of September and into early October. Motorist should expect minor delays.

    Work planned week of September 28 to October 2

    • Asphalt paving   

    • Line painting

    Work completed the week of September 21 to September 25 

    • The concrete curb was completed  

    • Gravel filled around curb (below asphalt) 

    Community impact

    • Single lane closures will remain throughout the month of September and into early October. Motorist should expect minor delays.

  • Project Update - September 21

    Share Project Update - September 21 on Facebook Share Project Update - September 21 on X (formerly Twitter) Share Project Update - September 21 on Linkedin Email Project Update - September 21 link

    Work planned Week of September 21 to September 25

    • Installation of the new concrete curb and asphalt median, weather permitting.
    • Asphalt paving around the new median will follow.

    Work completed Week of September 14 to September 18

    • Concrete barriers and asphalt were removed and a gravel base for the new median was placed and compacted.

    Community impacts

    • Single-lane closures in both directions will remain throughout the month of September and early October.

    Work planned Week of September 21 to September 25

    • Installation of the new concrete curb and asphalt median, weather permitting.
    • Asphalt paving around the new median will follow.

    Work completed Week of September 14 to September 18

    • Concrete barriers and asphalt were removed and a gravel base for the new median was placed and compacted.

    Community impacts

    • Single-lane closures in both directions will remain throughout the month of September and early October.
  • Project Update - September 14

    Share Project Update - September 14 on Facebook Share Project Update - September 14 on X (formerly Twitter) Share Project Update - September 14 on Linkedin Email Project Update - September 14 link

    Work planned for the week of September 14 to September 18

    • Asphalt will be removed where the concrete median is being installed
    • Gravel will be placed and tamped
    • Concrete forms will be created and installed

    Work completed the week of September 7 to September 11

    • Single lane closures set up in both directions
    • All concrete barriers have been removed

    Community impact

    • Single lane closures will remain throughout the month of September and into early October. Motorist should expect minor delays

    Work planned for the week of September 14 to September 18

    • Asphalt will be removed where the concrete median is being installed
    • Gravel will be placed and tamped
    • Concrete forms will be created and installed

    Work completed the week of September 7 to September 11

    • Single lane closures set up in both directions
    • All concrete barriers have been removed

    Community impact

    • Single lane closures will remain throughout the month of September and into early October. Motorist should expect minor delays
  • Project Update - September 4

    Share Project Update - September 4 on Facebook Share Project Update - September 4 on X (formerly Twitter) Share Project Update - September 4 on Linkedin Email Project Update - September 4 link

    September 4 Update

    Work planned week of September 7 to September 11

    • Work will be starting this week on Muskoka Road 118 between Balls Drive and Westmall Road.
    • Work for this week will include installation of traffic control and site setup, removal of the existing concrete barriers and the start of asphalt removals.

    Community impact

    • East-bound and west-bound will each be reduced to one lane during construction.
    • Motorists should expect delays and add additional time to travel plans.

    September 4 Update

    Work planned week of September 7 to September 11

    • Work will be starting this week on Muskoka Road 118 between Balls Drive and Westmall Road.
    • Work for this week will include installation of traffic control and site setup, removal of the existing concrete barriers and the start of asphalt removals.

    Community impact

    • East-bound and west-bound will each be reduced to one lane during construction.
    • Motorists should expect delays and add additional time to travel plans.