Project Update - September 28
Work planned week of September 28 to October 2
Asphalt paving
Line painting
Work completed the week of September 21 to September 25
The concrete curb was completed
Gravel filled around curb (below asphalt)
Community impact
Single lane closures will remain throughout the month of September and into early October. Motorist should expect minor delays.