Project Update - October 2

Temporary Barrier Installation Complete

Work completed week of September 28 to October 2

  • Crews placed new asphalt between the curbs and to tie into existing asphalt.
  • Old traffic paint in the middle of the road was removed and new traffic paint lines were installed.
  • Temporary traffic control measures were removed and both lanes of traffic were opened in each direction.

Community impact

  • Both lanes of traffic in each direction are now reopened.