February 24 2023
Funding application submitted to CMHC
March → April 2023
Building design and site servicing planning
May 16 2023
Tree cutting Request for Quote (RFQ) released
Tree cutting RFQ closed May 31, 2023
June 06 2023
Tree cutting contract awarded
June 19 2023
Tree cutting, grubbing and soil erosion controls commences
April 03 2023
Minor variance for height granted by Town of Bracebridge
June 12 2023
Site Plan Application Submitted to the Town of Bracebridge
July 17 2023
Site preparation including tree cutting and erosion controls completed
August 08 2023
Conditional Site Plan Approval Issued by Town of Bracebridge
September 2023
Seek alternative funding sources