Work planned week of September 14 to September 18

  • Hwy 117 surface paving
  • Pave raised intersections at crosswalk locations
  • Crosswalk electrical work and pole installation

Work completed week of September 7 to September 11

  • Crews finished pouring concrete landing pads in this area, which are small, flat concrete surfaces that give people a stable, level spot to step before/after sitting on the new Baysville park benches, once those are installed
  • Sidewalk and curb completion

Community impacts

  • Motorists can continue to expect minor delays along Muskoka Road 117 as this work continues
  • Single lane closures will occur during paving