Weekly Project Update - September 14
Work planned week of September 14 to September 18
- Hwy 117 surface paving
- Pave raised intersections at crosswalk locations
- Crosswalk electrical work and pole installation
Work completed week of September 7 to September 11
- Crews finished pouring concrete landing pads in this area, which are small, flat concrete surfaces that give people a stable, level spot to step before/after sitting on the new Baysville park benches, once those are installed
- Sidewalk and curb completion
Community impacts
- Motorists can continue to expect minor delays along Muskoka Road 117 as this work continues
- Single lane closures will occur during paving