Weekly Project Update - October 26
Work planned week of October 26 to October 30
- Site cleanup and maintenance will continue as the project area is prepared for winter shutdown.
- Line painting for the roadway and pedestrian walkways may take place if weather conditions permit.
Work completed week of October 19 to October 23
- The flagpole has been installed in the roundabout, and pedestrian crosswalk signals and crossings have been set up.
- Site cleanup activities have been completed.
Community impacts
- Motorists can continue to expect minor delays along Muskoka Road 117 as this work continues.