Work planned week of October 5 to October 9
- Construction on the raised intersections
- Site will continue to be cleaned.
- Site will be hydroseeded / receive sod.
Work completed week of September 28 to October 2
- Raised intersection designs are being reviewed
- Site Cleaned
Community impacts
- Motorists can continue to expect minor delays along Muskoka Road 117 as this work continues.
- Single lane closures will occur during paving.