Weekly Project Update - November 9
Work planned week of November 9 to November 13
- Final pavement markings, including the yellow centreline, white shoulder lines, and crosswalk markings at the roundabout and pedestrian crossings, are planned for installation. Painting is weather dependent and will be completed when conditions are dry, as rain prevents roadway markings from being applied.
Work completed week of November 2 to November 6
- Flagpole installation in the centre of the roundabout completed
- Crosswalks at University St and Bay St set up completed and will be put into service when pavement markings are completed.
Community impacts
- Motorists can expect the possibility of minor delays along Muskoka Road 117 as this work continues.
Share Weekly Project Update - November 9 on Facebook
Share Weekly Project Update - November 9 on X (formerly Twitter)
Share Weekly Project Update - November 9 on Linkedin
Email Weekly Project Update - November 9 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends