May 7, 2026 Update:
Here's a look at work planned for the remainder of 2026:
The roundabout and underground roadwork between Dickie Street and Bay Street are both on track to wrap up by the end of spring/early summer 2026.
From there, crews will shift to surface roadwork from MR2 to Bay Street, followed shortly after by a phase covering MR2 to University Street in mid-summer.
As summer winds down, the focus will turn to landscaping and streetscaping, giving the corridor the polished, finished look the community has been waiting for.
We're aiming for full contract completion in winter 2026.
Please note that all dates and durations are subject to change due to weather, supply availability, or other unforeseen circumstances. Check back here for the latest updates.