September 2026 Updates

September 14 Update

Work planned week of September 14 to September 18

  • The contractor will continue installing watermain, storm sewer and sanitary sewer laterals.

Work completed week of September 7 to September 11

  • The contractor continued installation of watermain and storm sewer.

Community impacts

  • Trisan plans to work Saturdays for the remaining duration of the project.
  • Pedestrian access through the construction site will be changing in advance of sidewalk removals. Please watch for updated signage.


September 4 Update

Work planned week of September 7 to September 11

  • Continue installing watermain between Mary and John Street.
  • Complete sanitary sewer services east of John Street.

Work completed week of August 31 to September 4

  • Continued installation of watermain from Sarah Street to the east side of Mary Street

Community impacts

  • Bay Street remains closed.
  • Pedestrian access through the construction site will be changing in advance of sidewalk removals on the south side of Bay Street. Please watch for updated signage through the construction site.
Share September 2026 Updates on Facebook Share September 2026 Updates on X (formerly Twitter) Share September 2026 Updates on Linkedin Email September 2026 Updates link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>