Weekly Project Update - October 19
Work planned week of October 19 to October 23
- Ongoing structural steel repairs, install dowels, wire mesh, and pour another section of concrete refacing along the retaining wall.
- Application of protective coatings on truss members along the Pre-Muskoka crossing.
Work completed week of October 12 to October 16
- The contractor continued the Ecclestone Drive concrete retaining wall refacing work by removing forms.
- The crew also completed the enclosure at pre-Muskoka and continued permanent structural steel repair work.
- The coating subcontractor mobilized to site, sandblasted and primed the pre-Muskoka crossing truss.
Community impacts
- There are no new impacts for residents or pedestrians this week.
Share Weekly Project Update - October 19 on Facebook
Share Weekly Project Update - October 19 on X (formerly Twitter)
Share Weekly Project Update - October 19 on Linkedin
Email Weekly Project Update - October 19 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends