Weekly Project Update - October 19

Work planned week of October 19 to October 23

  • Ongoing structural steel repairs, install dowels, wire mesh, and pour another section of concrete refacing along the retaining wall.
  • Application of protective coatings on truss members along the Pre-Muskoka crossing.

Work completed week of October 12 to October 16

  • The contractor continued the Ecclestone Drive concrete retaining wall refacing work by removing forms.
  • The crew also completed the enclosure at pre-Muskoka and continued permanent structural steel repair work.
  • The coating subcontractor mobilized to site, sandblasted and primed the pre-Muskoka crossing truss.

Community impacts

  • There are no new impacts for residents or pedestrians this week.
Share Weekly Project Update - October 19 on Facebook Share Weekly Project Update - October 19 on X (formerly Twitter) Share Weekly Project Update - October 19 on Linkedin Email Weekly Project Update - October 19 link