Weekly Project Update - September 28
Work planned week of September 28 to October 2
Concrete Work: Pour another section of concrete refacing along the Ecclestone Drive retaining wall.
Steel Repairs: Continue making permanent repairs to the structural steel.
Work completed week of September 21 to September 25
Work continued on repairing and updating the concrete retaining wall along Ecclestone Drive.
Bridge Profile: The bridge was lifted and adjusted to improve its position and alignment.
Permanent repairs to the bridge's structural steel resumed after the lifting work was completed.
Community impacts
There are no new impacts for residents or pedestrians this week.
Share Weekly Project Update - September 28 on Facebook
Share Weekly Project Update - September 28 on X (formerly Twitter)
Share Weekly Project Update - September 28 on Linkedin
Email Weekly Project Update - September 28 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends