Weekly Project Update - September 14
Work planned week of September 14 to September 18
- The contractor will continue repairs to the permanent structural steel.
- Installation of dowels and wire mesh is planned to support upcoming concrete work.
- The contractor will form another section of concrete refacing along the retaining wall.
Work completed week of September 7 to September 11
- The contractor finished removing the permanent structural steel components. Cleaning, sandblasting, and priming of the existing steel began in preparation for installing new steel components.
- Forms were removed from the Ecclestone Drive concrete retaining wall refacing.
Community impacts
- There are no new impacts for residents or pedestrians this week.
Share Weekly Project Update - September 14 on Facebook
Share Weekly Project Update - September 14 on X (formerly Twitter)
Share Weekly Project Update - September 14 on Linkedin
Email Weekly Project Update - September 14 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends