June 1, 2026 Update:
Work projected between June 1 and June 5:
- Installation of fencing along the sidewalk and set up traffic control for delivery of spine beams for temporary jacking support at Silver Bridge site.
- Concrete curing and dowel installation at Ecclestone Drive Retaining Wall.
- Installation of structural steel on south temporary footing.
- Dowel installation at Ecclestone Drive Retaining Wall.
- Ongoing temporary jacking support preparation.
- Installation of structural steel on south temporary footing.
- Dowel installation at Ecclestone Drive Retaining Wall.
May 25, 2026 Update:
Work projected between May 25 and May 29 will include:
- Removal of U1(9)-L1(9) members for jacking connections at the Silver Bridge site.
- Installation of dowels and formwork for retaining wall refacing at Ecclestone Drive.
- Installation of temporary support structural steel
Installation of concrete pad structures.
May 15, 2026 Update:
Work projected between May 19 and May 22:
- Establishing reinforcing steel and formwork for south abutment temporary jacking footing
- Installation of additional truss member reinforcing at Silver Bridge site
- Installation of wire mesh and dowels at Ecclestone Drive Retaining Walls
- Place concrete for South abutment temporary jacking footing at Silver Bridge site
- Milestone inspection for completed structural support and truss reinforcing works
- Curing concrete for south abutment temporary jacking footing
- Field templating jacking connections at Silver Bridge site
May 8, 2026 Update:
Work projected between May 11 and May 15, 2026:
- Installation and pouring of concrete to support temporary structural work at the north end of the bridge
- Ongoing strengthening of the bridge’s steel truss structure
- Continued work on retaining walls near Ecclestone Drive, including installing reinforcing connections
April 27, 2026 Update:
Work completed between April 20 and April 24, 2026:
- Continued partial depth concrete removals from retaining walls
- Installed scaffolding / access for truss strengthening
- Started truss strengthening
Work projected between April 27 and May 1, 2026:
- Install additional access and scaffolding for truss strengthening
- Continue truss member reinforcing
- Complete partial depth concrete removal on wall
April 17, 2026 Update:
Monday, April 20 - Crews will be adding reinforcement to the bridge's structural supports and setting up access for workers. At the Ecclestone Drive retaining walls, workers will be removing sections of concrete and setting up site access.
Tuesday, April 21 - Crews will continue adding reinforcement to the bridge's structural supports. At the Ecclestone Drive retaining walls, work continues on concrete removal, including measuring and inspecting the areas where concrete has been removed to determine if deeper removal is needed.
Wednesday, April 22 to Friday, April 24 - Crews will continue adding reinforcement to the bridge's structural supports. At the Ecclestone Drive retaining walls, workers will be doing more extensive concrete removal.
April 10, 2026 Update:
Construction work on Silver Bridge for the week of April 13 to 17 activities include:
Monday, April 13: Scaffolding and access equipment will be installed to support upcoming structural strengthening work. Crews will begin removing sections of concrete from the retaining walls and setting up site access.
Tuesday, April 14: Bracing and blocking will be installed, and structural strengthening of the bridge trusses will begin. Concrete removal and access work will continue with the retaining walls.
Wednesday, April 15 to Friday, April 17: Structural strengthening of the bridge trusses will continue. Concrete removal and access work will continue with the retaining walls.
Feb. 3, 2026 Update:
A detailed structural review and rehabilitation plan was completed and repair work is now underway.
Clearwater Structures Inc. are on site this week installing a temporary support structure that will be used during construction. The bridge is scheduled to reopen by the end of 2026.