Weekly Project Update - June 29 to July 5

Work planned week of June 29 to July 5

  • Installation of the Spine beam, a temporary structural “backbone” for the engineered jacking system.

  • Concrete ballast blocks will be delivered to the site.

  • Crews will continue placing concrete in the retaining wall and preparing sections for the next phase of wall resurfacing.

Work completed week of June 22 to 28

  • Crews continued installing temporary steel supports, including vertical supports at the bridge piers and jacking supports.

  • The Spine beams (temporary structural “backbone”) were delivered to the site.

  • Retaining wall resurfacing along Ecclestone Drive continued, with dowel and mesh installation now complete.

Community impacts

  • There are currently no new community impacts to note.