Weekly Project Update - June 29 to July 5
Work planned week of June 29 to July 5
Installation of the Spine beam, a temporary structural “backbone” for the engineered jacking system.
Concrete ballast blocks will be delivered to the site.
Crews will continue placing concrete in the retaining wall and preparing sections for the next phase of wall resurfacing.
Work completed week of June 22 to 28
Crews continued installing temporary steel supports, including vertical supports at the bridge piers and jacking supports.
The Spine beams (temporary structural “backbone”) were delivered to the site.
Retaining wall resurfacing along Ecclestone Drive continued, with dowel and mesh installation now complete.
Community impacts
There are currently no new community impacts to note.