August 2026- MOPR Update

The Muskoka Official Plan Review has been underway since 2024 and is a consolidation of a significant amount of work and we understand this can be a lot to navigate. For a road map of Components 1 through 5 and how we have got where we are please see the below chart!

Component

Stage

Date

Staff Reports

Presentations

Component 1: Growth Strategy

Background Report

November 21, 2024

Introduction of Component 1

March 20, 2025

Open House

June 10, 2025

Public Meeting

June 19, 2025

Approval of Component 1 for inclusion

July 24, 2025

Component 2: Resort Development

Introduction of Component 2

November 21, 2024

Open House

April 16, 2025

Public Meeting

April 24, 2025

Public Consultation Outcomes

July 24, 2025

Approval of Component 2 for inclusion

October 23, 2025

Component 3: Environmental Resiliency

Introduction of Component 3

November 20, 2025

Open House

December 11, 2025

Public Information Centre

December 11, 2025

Approval of Component 3 for inclusion

February 19, 2026

Public Consultation Outcomes

June 18, 2026

Public Information SessionsJuly 23, 2026

Component 4: Lake System Health

Background Report

October 24, 2026

Introduction of Component 4

November 20, 2025

Public Consultation Updates

April 24, 2025

Open House

December 11, 2025

Public Information Centre

December 11, 2025

Approval of Component 4 for inclusion

February 19, 2026

OPA 61Open HouseMay 12, 2026
Link
Public MeetingMay 21, 2026