September 28 - Update
Work planned week of September 28 to October 2
The pipe bursting subcontractor experienced a delay in mobilizing to the site and is now scheduled to begin work on September 28.
The contractor will complete the pipe bursting and replacement of the existing sanitary sewer south of Rogers Cove Drive.
Work completed week of September 21 to September 25
Crews completed watermain connections and installed new water services to properties.
Community impacts
Paving of King William Street from Highway 60 to Rogers Cove Drive is scheduled to take place during overnight road closures on October 13, 14, 15 and 16 (new dates). A full road closure will be required each night to ensure the work can be completed safely and efficiently.
Additional details regarding the closure and paving schedule will be communicated as the work date approaches.
We thank residents and businesses for their patience and cooperation as we complete this important infrastructure upgrade.