September 28 - Update

Work planned week of September 28 to October 2

  • The pipe bursting subcontractor experienced a delay in mobilizing to the site and is now scheduled to begin work on September 28.

  • The contractor will complete the pipe bursting and replacement of the existing sanitary sewer south of Rogers Cove Drive.

Work completed week of September 21 to September 25

  • Crews completed watermain connections and installed new water services to properties.

Community impacts

  • Paving of King William Street from Highway 60 to Rogers Cove Drive is scheduled to take place during overnight road closures on October 13, 14, 15 and 16 (new dates). A full road closure will be required each night to ensure the work can be completed safely and efficiently.

  • Additional details regarding the closure and paving schedule will be communicated as the work date approaches.

  • We thank residents and businesses for their patience and cooperation as we complete this important infrastructure upgrade.