September 14 Project Update

Work planned week of September 14 to September 18

  • Contractor will begin watermain commissioning
  • Crews will prepare for pipe bursting of the sanitary sewer south of Rogers Cove by setting up a temporary sanitary sewer by-pass

Work completed week of September 7 to September 11

  • Crews continued installing new sanitary sewer infrastructure and watermain

Community impacts

  • Traffic lanes will be shifted toward the center of the roadway as construction progresses, and motorists should follow all posted signage and traffic control measures
  • From September 21 to September 25, work is expected to occur over two daily shifts, with night work beginning on Sunday night (September 20) to complete watermain connections and advance the project schedule. Affected businesses will be receiving notice 10 days prior to the water disruption