October 26 - Update
Work planned week of October 26 to October 30
- Continued installation of underground infrastructure south of Rogers Cove towards Pet Valu
- Sanitary lateral connections will be made moving southbound towards 69 King William Street
- Installation of stormwater containment separator
- Stormwater and catch basin installations
- Rogers Cove traffic light installations - underground work
- Four way stop at King William and Rogers Cove is being installed and will stay in place until traffic lights are reinstated at Rogers Cove
- Traffic is to be anticipated to flip mid to late next week to facilitate the installation of the water main
- Begin installation of new water main pipes from in front of Canadian Tire Gas Bar to the south side of the north mall entrance
Work completed week of October 19 to October 23
- Roadway improvements continued, including boulevards and final asphalt paving on King William Street between Hwy #60 and Rogers Cove Drive, and ongoing road reconstruction south of Rogers Cove Drive in preparation for future paving.
- Underground infrastructure upgrades progressed, with new sanitary sewer service connections installed and continued storm drainage improvements, including new catch basins, maintenance structures, and storm sewer piping.
- Asphalt testing, road maintenance and pothole repairs completed.
Community impacts
- A traffic pattern change is anticipated beginning in the middle of the week. Traffic will shift from southbound lanes on King William to northbound lanes.
- A single northbound and southbound lane remains in effect on King William Street through the construction limits.
Share October 26 - Update on Facebook
Share October 26 - Update on X (formerly Twitter)
Share October 26 - Update on Linkedin
Email October 26 - Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends