October 2 - Update
Work planned week of October 5 to October 9
Concrete sidewalk installation will begin along King William Street from Rogers Cove Drive north toward Highway 60.
Trenchless sanitary sewer replacement work will continue, with crews installing new sanitary sewer pipe with pipe bursting technique.
Crews will continue forcemain installation, storm sewer pipe and structure construction, and road base rehabilitation throughout the project area.
Work completed week of September 28 to October 2
Trenchless sanitary sewer replacement progressed, with new sewer pipe installed using pipe-bursting techniques.
New concrete curb and gutter was constructed along sections of King William Street between Highway 60 and Rogers Cove Drive, while grading and granular base placement continued in preparation for upcoming sidewalk construction.
Community impacts
Overnight paving of King William Street between Highway 60 and Rogers Cove Drive is scheduled for October 13, 14, 15, and 16, requiring a full road closure each night.
Detour routes will be posted, and additional details regarding the closures and paving schedule will be communicated as the work dates approach.
We thank residents, businesses, and motorists for their continued patience and cooperation as this important infrastructure project progresses.