October 12 - Update

Work planned week of October 12 to October 16

  • Installation of storm and sanitary sewer infrastructure, including maintenance holes, catch basins, and associated underground piping.
  • Continuation of sanitary sewer pipe bursting operations south of Rogers Cove Drive.
  • Overnight paving operations requiring a full road closure from October 13 to 16, between 10:00 p.m. and 6:00 a.m. each night. Detour routes are signed.

Work completed week of October 5 to October 9

  • New sidewalks were completed on both sides of King William Street, improving pedestrian connectivity and accessibility.
  • Foundations for new traffic signal poles and the traffic signal control cabinet were installed to support future intersection improvements.
  • Sanitary sewer replacement continued south of Rogers Cove Drive, while road reconstruction progressed through granular base placement, grading, and compaction in preparation for paving.

Community impacts

  • Overnight paving of King William Street between Highway 60 and Rogers Cove Drive is scheduled for October 13, 14, 15, and 16. A full road closures will be required each night to allow the work to be completed safely and efficiently.
  • Detour routes will be clearly signed, and advance notice signage has been installed throughout the project area.
  • We thank residents, businesses, and the travelling public for their continued patience and cooperation as this important infrastructure improvement project progresses.