June 29, 2026 Project Update
Work planned week of June 29 to July 3
- Once water quality testing is complete, crews will begin switching water services to the temporary water supply. Water interruption notices were delivered to affected businesses on June 25, 2026.
- Excavations will begin in the north section of the project area to prepare for underground pipe replacement.
- A temporary sewer bypass system will be installed to maintain sanitary sewer service while sanitary sewer is replaced.
Work completed week of June 22 to June 26
- Progress & safety: Crews located utilities, began testing the temporary watermain, and installed safety fencing to protect pedestrians and drivers.
- Road conditions: Potholes were repaired, the road was regraded, and recycled asphalt was added to improve driving through the zone.
- Traffic management: Signal timing was actively monitored and adjusted with MTO to maintain traffic flow.
Community impacts
- Access & traffic: Businesses remain open and accessible; one lane each direction is maintained, but delays are expected—plan extra travel time.
- Monitoring & scheduling: Traffic signals are being monitored/adjusted, and construction (including Canada Day work) continues to stay on schedule.
- Water service updates: Some businesses will have temporary water interruptions; notices have been delivered and the contractor will communicate directly with those affected.
Share June 29, 2026 Project Update on Facebook
Share June 29, 2026 Project Update on X (formerly Twitter)
Share June 29, 2026 Project Update on Linkedin
Email June 29, 2026 Project Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends