June 29, 2026 Project Update

Work planned week of June 29 to July 3

  • Once water quality testing is complete, crews will begin switching water services to the temporary water supply. Water interruption notices were delivered to affected businesses on June 25, 2026.
  • Excavations will begin in the north section of the project area to prepare for underground pipe replacement.
  • A temporary sewer bypass system will be installed to maintain sanitary sewer service while sanitary sewer is replaced.


Work completed week of June 22 to June 26

  • Progress & safety: Crews located utilities, began testing the temporary watermain, and installed safety fencing to protect pedestrians and drivers.
  • Road conditions: Potholes were repaired, the road was regraded, and recycled asphalt was added to improve driving through the zone.
  • Traffic management: Signal timing was actively monitored and adjusted with MTO to maintain traffic flow.

Community impacts

  • Access & traffic: Businesses remain open and accessible; one lane each direction is maintained, but delays are expected—plan extra travel time.
  • Monitoring & scheduling: Traffic signals are being monitored/adjusted, and construction (including Canada Day work) continues to stay on schedule.
  • Water service updates: Some businesses will have temporary water interruptions; notices have been delivered and the contractor will communicate directly with those affected.