June 15, 2026 Project Update

North view of project site.Work Planned: June 15 to 19, 2026

  • Crews will finish locating and confirming underground utilities along the corridor.
  • Temporary water service will be installed. Residents and businesses will receive 10 days' notice before the temporary water main is connected.
  • Depending on construction progress, crews may begin replacing the road's underlying base layers on the north side of the northbound lane. This work may also include installing new stormwater pipes and catch basins.

Work Completed: June 8 to 11, 2026

  • Traffic was shifted to the southbound lane to allow work to begin on the northbound side.
  • Underground utility and water service lines were located at several points along both lanes.
  • Removal of the northbound lane is complete, included removing asphalt pavement, concrete curbs, traffic islands, and sidewalks.
  • Temporary traffic signals for vehicles and pedestrians were installed, and the existing traffic lights were covered and taken out of service.