July 6, 2026 Project Update

Work planned week of July 6 to July 10

  • Contractor will finish setup and testing of temporary sanitary bypass system.
  • Excavation at the north limit of the project will begin for new maintenance hole installation.
  • Work will begin to replace existing sanitary sewer pipes using trenchless methods.

Work completed week of June 29 to July 3

  • Multiple businesses were successfully connected to the temporary water system following approved water‑quality testing.
  • Crews began installing the temporary bypass system required ahead of upcoming sewer work.
  • Dust control, site fencing, pedestrian access improvements, and pothole repairs were completed to maintain safe movement of vehicles and pedestrians through the construction zone.

Community impacts

  • Businesses in the construction zone remain open and fully accessible to customers.
  • One lane remains open in each direction. Drivers should expect delays and plan for additional travel time.
  • Traffic conditions are being monitored and adjustments made as needed.
Share July 6, 2026 Project Update on Facebook Share July 6, 2026 Project Update on X (formerly Twitter) Share July 6, 2026 Project Update on Linkedin Email July 6, 2026 Project Update link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>