July 27 Project Update
Work planned week of July 27 to July 31
- Crews will continue installing the new sanitary sewer.
- Crews will begin forcemain installation.
Work completed week of July 20 to July 24
- Crews continued installation of the new sanitary sewer.
- A water valve was successfully installed at the north limit of the project using insertion
Manhole being installed. valve technology, allowing the work to be completed without shutting down the watermain. - Crews completed a watermain cut-and-cap operation, enabling the next phase of watermain replacement work to begin.
Community impacts
- Portable Variable Message Signs (PVMS) have been deployed to display real-time travel times through the construction zone, helping motorists make informed routing decisions.
- Drivers are reminded to follow all posted traffic control signage and keep intersections clear to maintain safe and efficient traffic flow through the work area.
- All businesses within the construction zone remain open and accessible to customers.
Share July 27 Project Update on Facebook
Share July 27 Project Update on X (formerly Twitter)
Share July 27 Project Update on Linkedin
Email July 27 Project Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends