July 27 Project Update

Work planned week of July 27 to July 31

  • Crews will continue installing the new sanitary sewer.
  • Crews will begin forcemain installation.

Work completed week of July 20 to July 24

  • Crews continued installation of the new sanitary sewer.
  • A water valve was successfully installed at the north limit of the project using insertionManhole being installed. valve technology, allowing the work to be completed without shutting down the watermain.
  • Crews completed a watermain cut-and-cap operation, enabling the next phase of watermain replacement work to begin.

Community impacts

  • Portable Variable Message Signs (PVMS) have been deployed to display real-time travel times through the construction zone, helping motorists make informed routing decisions.
  • Drivers are reminded to follow all posted traffic control signage and keep intersections clear to maintain safe and efficient traffic flow through the work area.
  • All businesses within the construction zone remain open and accessible to customers.