July 20 Project Update

Work planned Week of July 20 to 24

  • Crews to continue work on the replacement of the sanitary sewer systemRock breaking work underway.

Work completed Week of July 12 to 17

  • Crews excavated deep sanitary maintenance holes and replaced a section of sanitary sewer pipe using a method that avoids excavating
  • Crews completed nighttime watermain isolation work in preparation for watermain replacement
  • Safety measures like barriers, warning signs, and metal road plates were used to protect drivers and pedestrians.

Community impacts

  • Businesses in the construction zone remain open and fully accessible to customers, with one lane open in each direction drivers should expect delays and plan for additional travel time.
  • When travelling through the area, please follow all posted signs, use caution, and keep intersections clear. Your patience helps keep workers, drivers, and pedestrians safe.