July 20 Project Update
Work planned Week of July 20 to 24
- Crews to continue work on the replacement of the sanitary sewer system
Rock breaking work underway.
Work completed Week of July 12 to 17
- Crews excavated deep sanitary maintenance holes and replaced a section of sanitary sewer pipe using a method that avoids excavating
- Crews completed nighttime watermain isolation work in preparation for watermain replacement
- Safety measures like barriers, warning signs, and metal road plates were used to protect drivers and pedestrians.
Community impacts
- Businesses in the construction zone remain open and fully accessible to customers, with one lane open in each direction drivers should expect delays and plan for additional travel time.
- When travelling through the area, please follow all posted signs, use caution, and keep intersections clear. Your patience helps keep workers, drivers, and pedestrians safe.
Share July 20 Project Update on Facebook
Share July 20 Project Update on X (formerly Twitter)
Share July 20 Project Update on Linkedin
Email July 20 Project Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends