August 31 Project Update

Work planned week of August 31 to September 4

  • Continue construction of sanitary sewer, storm sewer and watermain.
  • Tentatively scheduled to complete watermain testing and commissioning by the end of the week.
  • Continue with road building in preparation of upcoming paving
  • Installation of underground traffic signal infrastructure.

Work completed week of August 24 to August 28

  • Installation of watermain and storm sewer.
  • Road grading and compaction to provide a stable surface for upcoming paving

Community impacts

  • Traffic patterns may change, depending on construction progress this week. Please follow all posted signage and traffic control measures.
  • All businesses remain open and accessible within the project limits.
  • There will be temporary water disruptions at some point in the coming weeks. Affected properties will be receiving a notice once the schedule for the disruptions has been confirmed.
Share August 31 Project Update on Facebook Share August 31 Project Update on X (formerly Twitter) Share August 31 Project Update on Linkedin Email August 31 Project Update link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>