August 31 Project Update
Work planned week of August 31 to September 4
- Continue construction of sanitary sewer, storm sewer and watermain.
- Tentatively scheduled to complete watermain testing and commissioning by the end of the week.
- Continue with road building in preparation of upcoming paving
- Installation of underground traffic signal infrastructure.
Work completed week of August 24 to August 28
- Installation of watermain and storm sewer.
- Road grading and compaction to provide a stable surface for upcoming paving
Community impacts
- Traffic patterns may change, depending on construction progress this week. Please follow all posted signage and traffic control measures.
- All businesses remain open and accessible within the project limits.
- There will be temporary water disruptions at some point in the coming weeks. Affected properties will be receiving a notice once the schedule for the disruptions has been confirmed.
Share August 31 Project Update on Facebook
Share August 31 Project Update on X (formerly Twitter)
Share August 31 Project Update on Linkedin
Email August 31 Project Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends