Work planned week of August 4 to August 7
Crews work to place a structure base and dewater the work area.
- Work planned includes:
- Sanitary pipe installations continuing south of Rogers Cove.
- Water line upgrades continue south of Rogers Cove.
- Installation of forcemain pipe (a pressurized pipe that carries wastewater. to the treatment plant) continues south of Rogers Cove.
- Storm sewer (rainwater pipe) installation continues north of Rogers Cove.
- Road reconstruction continues on northbound King William Street.
Work completed week of July 27 to July 31
- Crews installed new sanitary underground pipes, repaired existing sewer lines, and continued installing new piping.
- Sanitary sewer maintenance hole completed south of Rogers Cove.
Community impacts
- Crews will work Friday, August 7 in lieu of Monday, August 3.
- Traffic patterns may change the week of August 3 to 7, with a lane switch over to accommodate watermain installation, storm sewer installations and road base rehabilitation.
- Please watch for signage and reduce speed through the work zone.
Share August 3 Project Update on Facebook
Share August 3 Project Update on X (formerly Twitter)
Share August 3 Project Update on Linkedin
Email August 3 Project Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends