August 17 Project Update

Work planned week of August 17 to August 21

  • Crews will continue installing sanitary sewer via pipe bursting method and forcemain via open cut south of Rogers Cove.
  • Watermain replacement will continue between Highway 60 and Rogers Cove.
  • Storm sewer installation and placement of road base material will continue north of Rogers Cove.

Work completed week of August 10 to August 14

  • Crews continued work on maintenance holes including finishing the concrete work and final connections.
  • Crews installed storm sewer and placed and compacted new gravel road base to prepare for paving.
  • Crews began work on traffic signal installations at the Rogers Cove Drive intersection, including installing underground conduits.

Community impacts

  • Traffic lanes are anticipated to shift as work moves from the southbound side of the road to the northbound side.
  • Two-way traffic will continue to be maintained through the construction zone.
  • Motorists are reminded to follow all posted signage and traffic control measures through the work zone.