Construction Update - October 31, 2019

  • The storm and sanitary mains are planned to be installed in the intersection of Fairy Street and Chaffey Street next week.
    To accommodate this installation, Church Street will reopen to local traffic only and Fairy Street will be closed for approximately two weeks to accommodate the installation at this intersection.

  • During daytime working hours next week, flaggers will be directing traffic during this installation at the intersection at Fairy Street and Chaffey Street.
    After hours, temporary traffic lights will be used to ensure traffic moves through this area.

  • Left-hand turns will be permitted from John Street, onto King William Street - to allow improved access to Church Street from the north-side, on the eastbound King William lane.

  • Click here for a map, showing the above.

  • A Community Information Session has been scheduled on Tuesday, November 5, 2019 at 6:00 - 7:30pm (formal presentation at 6:15pm) at the Partner's Hall in the Algonquin Theatre.