Silver Bridge Closure and Recovery
The Silver Bridge in the Town of Bracebridge is fully closed to all vehicle and pedestrian traffic in both directions while construction is underway.
Detour Information
Detours: Detour routes are in place for safe travel to and from the Main Street area. Most drivers will only experience minimal delays.
Navigation Apps: Municipal 511 has been updated with detour information, helping to keep Google Maps and Waze current.
Updates: We’ll continue to share updates as they become available.
We appreciate your patience and cooperation as we work to ensure the safety of everyone using District infrastructure. Updates will be shared as they become available.
Background
In early January 2025, Bracebridge Operations staff noticed that the clearance for sidewalk equipment on the bridge looked different than usual. This prompted a closer inspection by District staff and a Senior Structural Engineer, which revealed some deformation in the bridge’s truss members.
A careful, expert-driven selection process
Before selecting Clearwater Construction, the District undertook a detailed and deliberate process to ensure the bridge could be safely rehabilitated and that the most qualified contractor was chosen.
This work included:
- Conducting an in-depth analysis of the failed structural condition and assessing the feasibility of rehabilitation.
- Evaluating how weight and loading were distributed across the bridge under the damaged condition.
- Consulting with industry experts to determine the safest and most effective rehabilitation approach.
- Requesting and reviewing expressions of interest from experienced heavy civil contractors and shortlisting the top three firms based on expertise and capacity.
- Interviewing shortlisted contractors, clarifying scope, and reviewing detailed technical and cost proposals before selecting a preferred partner.
This new, two-stage selection process was designed to secure the best industry expertise at the best overall value, ensuring the rehabilitation is completed safely, efficiently, and to the highest engineering standards.
The Silver Bridge in the Town of Bracebridge is fully closed to all vehicle and pedestrian traffic in both directions while construction is underway.
Detour Information
Detours: Detour routes are in place for safe travel to and from the Main Street area. Most drivers will only experience minimal delays.
Navigation Apps: Municipal 511 has been updated with detour information, helping to keep Google Maps and Waze current.
Updates: We’ll continue to share updates as they become available.
We appreciate your patience and cooperation as we work to ensure the safety of everyone using District infrastructure. Updates will be shared as they become available.
Background
In early January 2025, Bracebridge Operations staff noticed that the clearance for sidewalk equipment on the bridge looked different than usual. This prompted a closer inspection by District staff and a Senior Structural Engineer, which revealed some deformation in the bridge’s truss members.
A careful, expert-driven selection process
Before selecting Clearwater Construction, the District undertook a detailed and deliberate process to ensure the bridge could be safely rehabilitated and that the most qualified contractor was chosen.
This work included:
- Conducting an in-depth analysis of the failed structural condition and assessing the feasibility of rehabilitation.
- Evaluating how weight and loading were distributed across the bridge under the damaged condition.
- Consulting with industry experts to determine the safest and most effective rehabilitation approach.
- Requesting and reviewing expressions of interest from experienced heavy civil contractors and shortlisting the top three firms based on expertise and capacity.
- Interviewing shortlisted contractors, clarifying scope, and reviewing detailed technical and cost proposals before selecting a preferred partner.
This new, two-stage selection process was designed to secure the best industry expertise at the best overall value, ensuring the rehabilitation is completed safely, efficiently, and to the highest engineering standards.
-
Weekly Project Update - October 19
Share Weekly Project Update - October 19 on Facebook Share Weekly Project Update - October 19 on X (formerly Twitter) Share Weekly Project Update - October 19 on Linkedin Email Weekly Project Update - October 19 linkWork planned week of October 19 to October 23
- Ongoing structural steel repairs, install dowels, wire mesh, and pour another section of concrete refacing along the retaining wall.
- Application of protective coatings on truss members along the Pre-Muskoka crossing.
Work completed week of October 12 to October 16
- The contractor continued the Ecclestone Drive concrete retaining wall refacing work by removing forms.
- The crew also completed the enclosure at pre-Muskoka and continued permanent structural steel repair work.
- The coating subcontractor mobilized to site, sandblasted and primed the pre-Muskoka crossing truss.
Community impacts
- There are no new impacts for residents or pedestrians this week.
Work planned week of October 19 to October 23
- Ongoing structural steel repairs, install dowels, wire mesh, and pour another section of concrete refacing along the retaining wall.
- Application of protective coatings on truss members along the Pre-Muskoka crossing.
Work completed week of October 12 to October 16
- The contractor continued the Ecclestone Drive concrete retaining wall refacing work by removing forms.
- The crew also completed the enclosure at pre-Muskoka and continued permanent structural steel repair work.
- The coating subcontractor mobilized to site, sandblasted and primed the pre-Muskoka crossing truss.
Community impacts
- There are no new impacts for residents or pedestrians this week.
-
Weekly Project Update - October 12
Share Weekly Project Update - October 12 on Facebook Share Weekly Project Update - October 12 on X (formerly Twitter) Share Weekly Project Update - October 12 on Linkedin Email Weekly Project Update - October 12 linkWork planned week of October 12 to October 16
- Forming and pouring another section of concrete on the Ecclestone Drive retaining wall.
- Continuing permanent structural steel repair work on Silver Bridge.
- Starting the steel recoating process on the Pre-Muskoka Crossing bridge.
Work completed week of October 5 to October 9
- Concrete refacing of Ecclestone Drive retaining wall.
- Structural steel repair work on Silver Bridge.
- Installation of access and enclosures for structural steel coating on the Pre-Muskoka Crossing bridge.
Community impacts
- There are no new impacts for residents or pedestrians this week.
Work planned week of October 12 to October 16
- Forming and pouring another section of concrete on the Ecclestone Drive retaining wall.
- Continuing permanent structural steel repair work on Silver Bridge.
- Starting the steel recoating process on the Pre-Muskoka Crossing bridge.
Work completed week of October 5 to October 9
- Concrete refacing of Ecclestone Drive retaining wall.
- Structural steel repair work on Silver Bridge.
- Installation of access and enclosures for structural steel coating on the Pre-Muskoka Crossing bridge.
Community impacts
- There are no new impacts for residents or pedestrians this week.
-
Weekly Project Update - Oct 2
Share Weekly Project Update - Oct 2 on Facebook Share Weekly Project Update - Oct 2 on X (formerly Twitter) Share Weekly Project Update - Oct 2 on Linkedin Email Weekly Project Update - Oct 2 linkWork planned week of October 5 to October 9
Fabrication and installation of new structural steel for repair areas, including installation of new truss connection assemblies and replacement of deteriorated sections of the main bottom member of the truss.
Preparation for and placement of another section of concrete refacing along the Ecclestone Drive retaining wall.
Work completed week of September 28 to October 2
Removal of deteriorated sections of the main bottom member of the truss and fabrication of new connection plate assemblies for structural steel repair areas.
Installation of steel dowels, mesh and wood formwork for the next section of concrete refacing on the Ecclestone Drive retaining wall.
Community impacts
There are no new impacts for residents or pedestrians this week.
Work planned week of October 5 to October 9
Fabrication and installation of new structural steel for repair areas, including installation of new truss connection assemblies and replacement of deteriorated sections of the main bottom member of the truss.
Preparation for and placement of another section of concrete refacing along the Ecclestone Drive retaining wall.
Work completed week of September 28 to October 2
Removal of deteriorated sections of the main bottom member of the truss and fabrication of new connection plate assemblies for structural steel repair areas.
Installation of steel dowels, mesh and wood formwork for the next section of concrete refacing on the Ecclestone Drive retaining wall.
Community impacts
There are no new impacts for residents or pedestrians this week.
-
Weekly Project Update - September 28
Share Weekly Project Update - September 28 on Facebook Share Weekly Project Update - September 28 on X (formerly Twitter) Share Weekly Project Update - September 28 on Linkedin Email Weekly Project Update - September 28 linkWork planned week of September 28 to October 2
Concrete Work: Pour another section of concrete refacing along the Ecclestone Drive retaining wall.
Steel Repairs: Continue making permanent repairs to the structural steel.
Work completed week of September 21 to September 25
Work continued on repairing and updating the concrete retaining wall along Ecclestone Drive.
Bridge Profile: The bridge was lifted and adjusted to improve its position and alignment.
Permanent repairs to the bridge's structural steel resumed after the lifting work was completed.
Community impacts
There are no new impacts for residents or pedestrians this week.
Work planned week of September 28 to October 2
Concrete Work: Pour another section of concrete refacing along the Ecclestone Drive retaining wall.
Steel Repairs: Continue making permanent repairs to the structural steel.
Work completed week of September 21 to September 25
Work continued on repairing and updating the concrete retaining wall along Ecclestone Drive.
Bridge Profile: The bridge was lifted and adjusted to improve its position and alignment.
Permanent repairs to the bridge's structural steel resumed after the lifting work was completed.
Community impacts
There are no new impacts for residents or pedestrians this week.
-
Weekly Project Update - September 21
Share Weekly Project Update - September 21 on Facebook Share Weekly Project Update - September 21 on X (formerly Twitter) Share Weekly Project Update - September 21 on Linkedin Email Weekly Project Update - September 21 linkWork planned Week of September 21 to September 25
- Continue permanent structural steel repairs on Silver Bridge.
- Install dowels and wire mesh and pour concrete refacing along the retaining wall.
Work completed Week of September 14 to September 18
- Continued the Ecclestone Drive concrete retaining wall refacing. Work included partial depth concrete removals, installation of dowels and mesh.
- Crews also began installing new formwork for the next section of concrete refacing.
Community impacts
There are no new impacts for motorists or pedestrians this week.
Work planned Week of September 21 to September 25
- Continue permanent structural steel repairs on Silver Bridge.
- Install dowels and wire mesh and pour concrete refacing along the retaining wall.
Work completed Week of September 14 to September 18
- Continued the Ecclestone Drive concrete retaining wall refacing. Work included partial depth concrete removals, installation of dowels and mesh.
- Crews also began installing new formwork for the next section of concrete refacing.
Community impacts
There are no new impacts for motorists or pedestrians this week.
-
Weekly Project Update - September 14
Share Weekly Project Update - September 14 on Facebook Share Weekly Project Update - September 14 on X (formerly Twitter) Share Weekly Project Update - September 14 on Linkedin Email Weekly Project Update - September 14 linkWork planned week of September 14 to September 18
- The contractor will continue repairs to the permanent structural steel.
- Installation of dowels and wire mesh is planned to support upcoming concrete work.
- The contractor will form another section of concrete refacing along the retaining wall.
Work completed week of September 7 to September 11
- The contractor finished removing the permanent structural steel components. Cleaning, sandblasting, and priming of the existing steel began in preparation for installing new steel components.
- Forms were removed from the Ecclestone Drive concrete retaining wall refacing.
Community impacts
- There are no new impacts for residents or pedestrians this week.
Work planned week of September 14 to September 18
- The contractor will continue repairs to the permanent structural steel.
- Installation of dowels and wire mesh is planned to support upcoming concrete work.
- The contractor will form another section of concrete refacing along the retaining wall.
Work completed week of September 7 to September 11
- The contractor finished removing the permanent structural steel components. Cleaning, sandblasting, and priming of the existing steel began in preparation for installing new steel components.
- Forms were removed from the Ecclestone Drive concrete retaining wall refacing.
Community impacts
- There are no new impacts for residents or pedestrians this week.
-
Weekly Project Update - September 4
Share Weekly Project Update - September 4 on Facebook Share Weekly Project Update - September 4 on X (formerly Twitter) Share Weekly Project Update - September 4 on Linkedin Email Weekly Project Update - September 4 linkWork planned week of September 7 to September 11
- Continue permanent structural steel repairs to the main truss now that the bridge is in the temporarily supported condition.
- Install wood formwork to complete another section of concrete refacing along the Ecclestone Drive retaining wall.
Work completed week of August 31 to September 4
- Removal of old structural steel components to be replaced.
- Sandblasting (high pressure air that blasts abrasive particles to clean a surface) and priming of existing steel to remain prior to installing new steel replacement components.
- Completed a concrete pour on the Ecclestone Drive retaining wall refacing.
Community impacts
- There are no new impacts for residents or pedestrians this week.
Work planned week of September 7 to September 11
- Continue permanent structural steel repairs to the main truss now that the bridge is in the temporarily supported condition.
- Install wood formwork to complete another section of concrete refacing along the Ecclestone Drive retaining wall.
Work completed week of August 31 to September 4
- Removal of old structural steel components to be replaced.
- Sandblasting (high pressure air that blasts abrasive particles to clean a surface) and priming of existing steel to remain prior to installing new steel replacement components.
- Completed a concrete pour on the Ecclestone Drive retaining wall refacing.
Community impacts
- There are no new impacts for residents or pedestrians this week.
-
Weekly Project Update - August 31
Share Weekly Project Update - August 31 on Facebook Share Weekly Project Update - August 31 on X (formerly Twitter) Share Weekly Project Update - August 31 on Linkedin Email Weekly Project Update - August 31 linkWork planned for week of August 31 to September 4
- Continue permanent structural steel repairs to the damaged members on the bottom side of the truss.
- Pour a section of concrete refacing along the Ecclestone Drive retaining wall.
Work completed week of August 24 to August 28
- Completed bridge jacking (lifting) and set bridge in its temporary position to facilitate structural steel repairs.
- Installed sidewalk strong backs (temporary supports) and began the removal of permanent structural steel components to be repaired.
Community impacts
No new impacts for motorists or pedestrians this week.
Work planned for week of August 31 to September 4
- Continue permanent structural steel repairs to the damaged members on the bottom side of the truss.
- Pour a section of concrete refacing along the Ecclestone Drive retaining wall.
Work completed week of August 24 to August 28
- Completed bridge jacking (lifting) and set bridge in its temporary position to facilitate structural steel repairs.
- Installed sidewalk strong backs (temporary supports) and began the removal of permanent structural steel components to be repaired.
Community impacts
No new impacts for motorists or pedestrians this week.
-
Weekly Project Update - August 24
Share Weekly Project Update - August 24 on Facebook Share Weekly Project Update - August 24 on X (formerly Twitter) Share Weekly Project Update - August 24 on Linkedin Email Weekly Project Update - August 24 linkWork planned for week of August 24 to August 28
Crews will:
- Continue placing concrete blocks on the south side and raise the bridge to its resting height,
- and begin structural steel repairs on the underside of the truss.
Work completed week of August 17 to August 21
- Crews finished installing the south spine beam, along with jacking support beams and plates and the jacks for raising the bridge
- Crews installed additional sidewalk supports and began jacking (lifting) the bridge to facilitate structural steel repairs to members on the underside of the truss.
Community impacts
- There are no new community impacts for this week.
Work planned for week of August 24 to August 28
Crews will:
- Continue placing concrete blocks on the south side and raise the bridge to its resting height,
- and begin structural steel repairs on the underside of the truss.
Work completed week of August 17 to August 21
- Crews finished installing the south spine beam, along with jacking support beams and plates and the jacks for raising the bridge
- Crews installed additional sidewalk supports and began jacking (lifting) the bridge to facilitate structural steel repairs to members on the underside of the truss.
Community impacts
- There are no new community impacts for this week.
-
Weekly Project Update - August 17
Share Weekly Project Update - August 17 on Facebook Share Weekly Project Update - August 17 on X (formerly Twitter) Share Weekly Project Update - August 17 on Linkedin Email Weekly Project Update - August 17 linkWork planned week of August 17 to August 21
- Crews will finish installing the jacking system at both ends of the bridge (equipment used to lift the bridge), including rollers, jacks, and transverse beams that run side to side across the bridge.
- Weather and progress permitting, the contractor expects to begin lifting the bridge later this week.
Work completed week of August 10 to August 14
- Crews finished installing the launching mechanism (equipment used to move large lifting beams into place) at the south end of the bridge and installed the south lifting beams.
- Crews built and poured a concrete ballast block at the north end for the lifting beams.
Community impacts
- No new community impacts are anticipated this week.
Work planned week of August 17 to August 21
- Crews will finish installing the jacking system at both ends of the bridge (equipment used to lift the bridge), including rollers, jacks, and transverse beams that run side to side across the bridge.
- Weather and progress permitting, the contractor expects to begin lifting the bridge later this week.
Work completed week of August 10 to August 14
- Crews finished installing the launching mechanism (equipment used to move large lifting beams into place) at the south end of the bridge and installed the south lifting beams.
- Crews built and poured a concrete ballast block at the north end for the lifting beams.
Community impacts
- No new community impacts are anticipated this week.
-
Phone 705-645-2100 Email mark.misko@muskoka.on.ca







